Rutherford County drivers will be some of the first to use I-24 Choice Lanes, but not until late 2034
The Morning Murfreesboro team
If you drive I-24 between Nashville and Murfreesboro, here's your timeline. At community meetings this week, TDOT released new details on the project, which adds two dynamically priced toll lanes in each direction along about 26 miles of the interstate. The first phase, from around Old Hickory Boulevard in Antioch to northwest of I-840 in Murfreesboro, is expected to open Nov. 22, 2034. The second follows on July 11, 2035.
TDOT's Paige Heintzman said this stretch goes first because it's "not as congested" and gives new users an eight-month window to get familiar. The new renderings put the lanes outside the existing ones instead of between them. WSMV spoke with Noble Place homeowner Jerry Stankevich, who worries the elevated lanes will sit extremely close to neighbors' houses. TDOT says the designs aren't final and could still change.
- Elevated roadway: about a third of the total miles, per DriveTN
- Right-of-way: acquisition underway for 17 properties
- Operator: DriveTN, whose business Ferrovial manages tolls elsewhere in the U.S.
Both phases are expected to open in 2034 and 2035
- Early 2027Additional right-of-way acquisitions will begin.
- Q2 2027Right-of-way meetings are expected in the second quarter.
- Nov. 2034The first phase is expected to open.
- July 2035The second phase is expected to open.
Source: Main Street Media of Tennessee
Sources: Main Street Media of Tennessee, wsmv.com